项目变更控制过程(二)

时间:2009-11-14 21:37 点击:801次 字体:[ ]




  Procedure(程序)
  Entry Criteria(开始条件)
  Change control board is established for the project.
  Baselined work products exist.
  The Originator has submitted a valid issue or change request with all necessary information to the CCB Chair.
  The change control tool sets the issue’s initial status to Submitted.
  已建立项目变更控制委员会。
  存在已基线化的工件。
  发起人提交正确的变更请求或将变更请求和所有必要的信息提交给变更控制委员会主席。
  变更控制工具将变更请求的初始状态设置为已提交。
  Tasks(任务)
  1. The CCB Chair assigns an Evaluator.
  1. 变更控制委员会主席指定一个评估人 。
  2. The Evaluator assesses the issue as to feasibility, whether it really pertains to the indicated project, whether a reported problem can be reproduced, an estimate of the labor hours needed to implement the change, and so on. For a requirement change, use the Impact Analysis Checklist for Requirements Changes, the Effort Estimation Worksheet for a Requirement Change, and the Impact Analysis Report Template. Change status to Evaluated.
  2. 评估人对变更请求进行可行性评估,判断其是否真正符合项目特征,被报告的问题是否能被重复产生,估计实施变更所需工作量等等。对一个需求变更,用影响分析检查表,工作量估计表,以及影响分析报告模板进行评估。改变状态为已评估。
  3. The CCB decides whether the requested change should be made (or the reported problem fixed) at this time, at some point in the future, or not at all. Input should be solicited from others potentially affected by the change before making the decision.
  3. 变更控制委员会决定此次提出的变更是否应实施(或已报告的问题是否应解决),或部分变更在将来解决,或根本不解决。 决定前必须从其他被变更影响的潜在方获取必要的意见。
  4. If the change was accepted, the CCB Chair assigns a Modifier, sets the status to Approved, enters any explanation in the Response attribute, and schedules the work. The Project Manager negotiates any necessary changes in project commitments with affected stakeholders. Tool sends e-mail to the assigned Modifier and the Originator.
  4. 如果接受变更请求,变更控制委员会主席会指定一个修改人,同时设置变更请求状态为已批准,并在回应属性中填入相应解释。项目经理在项目会议中同涉众协商任何必需的变更。变更控制工具发电子邮件给已指定的修改人和发起人。
  5. If the change was rejected, the CCB Chair sets the status to Rejected and enters an explanation of why in the Response attribute. Tool sends e-mail to the Originator and CCB Chair.
  5. 如果变更被拒绝,变更控制委员会主席设置变更状态为已拒绝并在回应属性中解释拒绝的原因。变更控制工具发电子邮件给发起人和变更控制委员会主席。
  6. The CCB Chair and the Originator determine whether formal verification of the change will be required, following the procedure in the Verification section. If so, they select the verification method to be used and the CCB Chair assigns a Verifier.
  6. 变更控制委员会主席和发起人决定是否需要对变更进行正式的验证,具体的步骤在下面的验证部分中描述。如果是,他们选择使用的验证方法并由变更控制委员会主席指定验证人。
  7. The Modifier makes the necessary changes in the affected work products and notifies any other affected parties if corresponding changes need to be made, such as user documentation, help screens, and tests.
  7. 修改人在受影响的工件中实施必要的变更,如果在其他方也需要实施相应变更则应通知所有其他受影响方,如用户文档、帮助屏幕、测试文档等。
  8. The Project Manager updates the project plans, task lists, and schedules to reflect the impact of the change on project work remaining to be done. The Project Manager revises any task dependencies as necessary.
  8. 项目经理更新项目计划,任务清单,和时间表,以反映变更对已做或在做工作的影响。如果需要,项目经理修订任务的依赖性。
  9. If it becomes apparent during the work that the requested change is not feasible after all, the Modifier notifies the CCB Chair, who may then set the status to Canceled. The Modifier backs out of any modifications made, restoring the work products to their previous baseline. Tool sends e-mail to the Originator, CCB Chair, Modifier, and Project Manager.
  9. 最后如果在工作期间发现需求变更是不可行的,修改人应通知变更控制委员会主席,由他作出取消决定并设置状态为已取消。修改人返回未做修改状态,恢复以前已基线化的工件。变更控制工具发电子邮件给发起人,变更控制委员会主席,修改人和项目经理。
  10. When the change is completed, the Modifier sets the status to Change Made, updates the issue in the database with appropriate notes in the Response attribute, and enters the hours of effort that were required to make the change in the Actual Hours attribute. Tool sends e-mail to the Originator and CCB Chair.
  10. 当变更完成时,修改人设置变更状态为实施变更,在回应属性中对更新的变更请求加入适当的注释,并在实际时间属性中输入实施变更所花的实际工作量。变更控制工具发电子邮件给发起人和变更控制委员会主席。
  Verification(验证)
  1. The Modifier notifies the Originator and Verifier (if one was assigned) that the change has been made and makes all modified work products available to the people responsible for verification.
  1. 修改人通知发起人和验证人(如果已经有指定的验证人)变更已经被实施,并且所有已修改的工件已经可以进行验证。
  2. The Verifier performs the agreed-upon verification steps.
  2. 验证人执行验证过程。
  3. If verification is successful, the Verifier sets the status to Verified.   Tool sends e-mail to the Originator and Modifier.
  3. 如果验证通过,验证人设置变更状态为已验证。变更控制工具发电子邮件给修改人和发起人。
  4. If verification is not successful, the Verifier sets the status back to Approved and describes the problem in the Response attribute. Tool sends e-mail to the Originator and Modifier. The process resumes with Task #7.
  4. 如果验证未通过,验证人设置变更状态为已批准并在回应属性中描述具体的问题。变更控制工具发电子邮件给修改人和发起人。此过程会从任务#7重新开始进行。
  5. For a problem report issue or an enhancement request issue, the Modifier installs the modified work product as appropriate and updates the product baseline. For requirements changes, the Modifier updates version numbers on all modified work products per the project’s version control procedure, checks them back into the version control system, updates requirements traceability information and requirements status attributes as necessary, and updates the requirements baseline.
  5. 对于一个问题报告或增加需求的发布,修改人安装已修改后的工件并更新产品基线。对于需求变更,修改人按照每个项目的版本控制程序更新所有已修改工件的版本号,如果需要应更新需求追溯信息和需求状态属性,并更新需求基线。
  6. The Modifier sets the status to Closed. Tool sends e-mail to the Originator and CCB Chair.
  6. 修改人设置变更状态为已结束。变更控制工具发电子邮件给发起人和变更控制主席。
  Change Control Status Reporting(变更控制状态报告) The CCB Chair generates a report at the end of each month summarizing the status of the contents of the change control database. These reports identify all status changes made in the previous month, list the status of all change requests that currently have a status other than Rejected or Closed, and indicate the level of change activity. The project leadership team reviews these reports to determine whether any corrective actions are necessary.
  变更控制委员会主席根据变更控制数据库的内容在月末汇总出变更控制数据的报告。这些报告表现出上一个月所有发生的变更的状态,列出当前所有需求变更的状态但已拒绝和已完成的除外,并指出变更活跃程度。项目管理组查看这些报告以确定每个活动的正确性。
  Exit Criteria(退出条件)
  o The status of the request is either Rejected or Closed.
  o The modified work products have been correctly installed into the appropriate locations.
  o The Originator, CCB Chair, and Project Manager have been notified of the current status.
  o Pertinent requirements traceability information has been updated.
  o 变更请求的状态为已拒绝或已结束。
  o 所有修改后的工件被正确安装到适当的位置。
  o 发起人、变更控制主席、和项目经理已被告知当前的状态。
  o 相关的需求追溯信息已被更新。
  Appendix(附件): Attributes Stored for Each Issue(每个变更请求应保存的属性)
Field (字段) How Set (执行人) Contents (内容)
Actual Hours
(实际时间)
Modifier
(修改人)
Actual labor hours of effort needed to implement the change.实际实现变更所花的工作时间。
Description
(描述)
Originator
(发起人)
Free-form text description of the change being requested. This cannot be changed after it is entered. If reporting a problem, enter the exact error message text observed here.对所提出的变更的文字描述。 如果确定后,此属性不能变更。 如果报告的是一个问题,应在此输入准确的错误信息。
Date Submitted
(提交日期)
System(系统) Date this issue was submitted to the tool.提交变更请求的日期。
Date Updated
(更新日期)
System(系统) Date this issue was most recently updated.更新变更请求最近的日期。
Estimated Hours
(估计时间)
Modifier(修改人) Estimated labor hours of effort needed to implement the change.估计实现变更所需的工作时间。
Implementation Priority
(实现优先级)
CCB Chair
(变更控制委员会主席)
Relative importance of making the change: Low (default), Medium, High.正在处理的变更的重要性:低(默认)、中、高。
Issue ID
(变更请求ID号)
System(系统) Sequence number assigned to the issue.分配给每个变更请求一个顺序号。
Issue Type
(变更类型)
Originator
(发起人)
Type of change request being created: Problem, Enhancement, Requirement Change, New Project.所建立的变更请求的类型,如错误报告、改进、需求变更,新项目。
Modifier
(修改人)
CCB Chair
(变更控制委员会主席)
Person who is assigned responsibility for implementing the change.被指定实施变更的负责人。
Originator
(发起人)
Originator
(发起人)
Originator’s name.发起人的姓名。
Originator E-Mail
(发起人电子邮件)
Originator
(发起人)
Originator’s e-mail address.发起人的电子邮件地址。
Originator Phone
(发起人电话)
Originator
(发起人)
Originator’s phone number。发起人的电话
Originator Priority
(发起人设置的优先级)
Originator
(发起人)
Originator’s relative importance of the change: Low, Medium, High.发起人赋予每个变更请求相应的重要性:低、中、高。
Planned Release
(已计划的发布)
CCB Chair
(变更控制委员会主席)
Product release number for which this approved change is scheduled, determined by CCB.由变更控制委员会决定已批准变更的产品发布号。
Product(产品) Originator
(发起人)
Name of the product or project in which a change is being requested or a problem reported.发生变更或已报告问题的项目或产品名称。
Problem Severity
(问题的严重性)
Originator
(发起人)
For a problem report, set severity of the change (see Table 1). Use N/A if this issue is not a problem report.对于已报告的问题设置变更的严重性(见表1)。如果这个变更请求不是问题报告则用N/A表示。
Response(回应) CCB Chair
(变更控制委员会主席), Modifier
(修改人)
Free-form text of responses made to the change request. Multiple responses can be made over time. Do not change existing responses.每个变更相对应的回应内容。随时记录所做地各种回应。不能更改已存在的回应。
Status(状态) Originator,
(发起人) Modifier(修改人)
Update current status of the change request as it moves through the states described in the Change Request Status section. Date of status changes and name of user making the update are shown automatically.更新变更请求的当前状态以符合在变更需求状态部分的描述。自动显示状态变更日期和更新用户的姓名。
Title(标题) Originator
(发起人)
One-line description of the issue.变更请求的简短描述。
Verifier
(验证人)
CCB Chair
(变更控制委员会主席)
Name of individual who is responsible for verifying that changes were made correctly.负责验证变更是否被正确实施的人员。
  Table 1. Problem Severity Descriptions.(表1,问题严重性描述)
Severity(严重性)
Examples(描述)
Minor(较轻) Cosmetic problem, usability improvement, unclear error messages; customer can live with the problem (default)表面问题,可用性改进,不清晰的错误信息;客户能使用有此类问题的系统(默认)
Major(重要) Problem adversely affects product functioning, but a workaround is available; customer will be annoyed; serious usability impairment; problem blocks some testing问题影响产品的功能,但某个工作区还是可用的;顾客感到厌烦;严重地损害可用性;问题阻碍了某些测试
Critical(严重) Product does not function at all or crashes; the wrong results are generated; further testing of the application is not possible产品根本不能运转或死掉;产生错误的结果;无法对系统进行进一步的测试
Emergency(紧急) Anything that requires a change to be made immediately, bypassing the change control process temporarily 任何需要立即实施的变更,可暂时绕过变更控制过程。


本文地址 : http://www.fengfly.com/plus/view-153241-1.html
标签: 项目 控制 过程 变更 Originator The To
------分隔线----------------------------
最新评论 查看所有评论
发表评论 查看所有评论
请自觉遵守互联网相关的政策法规,严禁发布色情、暴力、反动的言论。
评价:
表情:
验证码: